Introduction of New Supplementary Building Control Charges
New charges have been introduced for a range of supplementary services offered by Solihull Council's Building Control Section. Homeowners who undertake building work often fail to obtain a Completion Certificate. From the 31st January 2007, a fee will be payable to re-open archived cases for the purposes of issuing a Completion Certificate.
If you are selling property that has been altered or extended, you need to provide evidence to prospective purchasers that the building work has approved and inspected by a Building Control Body under the Building Regulations. This evidence is in the form of a Building Regulation Completion/Final Certificate and/or Approval Notice (called 'authorised documents' in The Home Information Pack Regulations 2006, due to come into force on the 1st June 2007)
Legal entitlement to a Completion Certificate is subject to conditions. In cases where the Council is not told that building work has been completed, or the building is occupied without addressing outstanding Building Regulation matters, a certificate is not issued.
Despite the best efforts of the Council's Building Control Surveyor's, many homeowners who undertake building work fail to obtain a Completion Certificate.
FROM THE 31ST JANUARY 2007, A FEE WILL BE PAYABLE TO RE-OPEN ARCHIVED CASES FOR THE PURPOSES OF ISSUING A COMPLETION CERTIFICATE.
Other charges are now payable where we are requested to withdraw a Building Regulation application and refund the application fee, or asked to re-direct inspection fee invoices.
|
DESCRIPTION |
Charge |
VAT |
Total |
|
|---|---|---|---|---|
|
ARCHIVED APPLICATIONS |
||||
|
Process request to re-open archived Building Control file, resolve case and issue Completion certificate |
£50.00 administration fee |
£8.75 |
£58.75 |
|
|
Each visit to site in connection with resolving archived Building Control Cases |
£50.00 per site visit |
£8.75 |
£58.75 |
|
|
WITHDRAW FULL PLANS APPLICATION AND REFUND FEES PAID |
||||
|
Process request |
£35.00 administration fee |
£6.13 |
£41.13 |
|
|
Without plans been checked |
Refund plan fee, less admin charge |
|||
|
With plans being checked , but no inspections |
Refund inspection fee (where applicable), less admin charge |
|||
|
With plans being checked , and inspections carried out |
Refund inspection fee, less admin charge + £50/site visit |
|||
|
WITHDRAW BUILDING NOTICE AND REFUND FEES PAID |
||||
|
Process request |
£35.00 |
£6.13 |
£41.13 |
|
|
Registered, but no details submitted and checked. No site visits carried out |
Refund BN fee, less admin charge |
|||
|
Registered with construction details submitted and checked. No inspections |
Refund inspection fee element, less admin charge |
|||
|
Registered, but no details submitted and checked. Site inspections carried out |
Refund plan fee element, less admin charge |
|||
|
Registered with construction details submitted and checked. Site inspections carried out |
Refund site fee element, less admin charge + £50/site visit |
|||
|
RE-DIRECT INSPECTION FEE INVOICE |
||||
|
Process request to re-invoice inspection fee to new addressee |
£35.00 administration fee |
£6.13 |
£41.13 |
|
For further information please contact Building Control
Telephone: 0121 704 6562