Building Safety Levy

The Building Safety Levy is a government charge on some new residential developments. The money raised will help fund building safety and improve unsafe buildings across England.

The levy will come into effect from 1 October 2026.

Where does the levy apply?

The levy applies to:

  • major residential developments – this means creating 10 or more new dwellings or 30 new bedspaces
  • works which create new residential floorspace
  • developers who are not registered non-profit providers of social housing
  • conversions or changes of use from non-residential to major residential developments

Exemptions

The levy does not apply to:

  • accommodation for domestic abuse victims
  • almshouses
  • armed forces accommodation
  • care homes and hospices
  • children’s homes and residential family centres
  • hospitals
  • hotels and hostels
  • monasteries, nunneries and similar establishments
  • prisons and secure accommodation
  • school accommodation
  • social housing
  • supported housing
  • temporary accommodation for homeless people
  • Ministry of Defence or Crown properties

How is the levy calculated?

The levy is charged based on the floor area of residential buildings 

Levy rates are set by the government and depend on:

  • the location of the development
  • if the development qualifies for the Previously Developed Land (PDL) discounted rate
  • the Gross Internal Area (GIA) of the chargeable floorspace

Charging rates for Solihull

Land typeRate (£ for square metre)
Previously developed land£17.56
Non-previously developed land   £35.12

Who is required to pay the levy?

The developer, the person or organisation carrying out the development, is responsible for paying the levy. 

The levy is charged on:

  • relevant building control full plans
  • initial notices
  • high rise building applications
  • works providing at least one dwelling or a bedspace in purpose-built student accommodation

Your application, or initial notice, may be rejected if you do not include information for the purpose of the levy. 

How to calculate and pay the levy

Apply

You must include Building Safety Levy information within your building control application.

This only applies if your application is submitted on or after 1 October 2026.

Submit a commencement notice

Before starting work, a commencement notice must be submitted within two working days with supporting levy information.

Council assessment

We will issue either a:

  • levy liability notice
  • notice of no charge

This will be issued within:

  • five weeks 
  • eight weeks - if a spot check is required 

Paying the levy

The levy must be paid in full.

Completion certificate

A completion certificate will only be issued once the levy has been paid.

Further information

Full guidance on the Building Safety Levy can be found on the government website: