As the physical highway widening works are substantial, there’s a requirement to divert, protect or alter numerous statutory utilities located within the widening corridor before major construction activities can begin.
These works are undertaken by the utility companies themselves and are subject to their own:
- programming constraints
- design approvals
- procurement processes
- national resource availability
Many of those have statuary process times that the council do not control.
The scheme requires diversions by the following utility providers:
- Openreach
- Severn Trent Water
- Cadent Gas
- Fulcrum Gas Networks
- Vodafone
- Virgin Media
- National Grid
Typical lead-in periods for utility diversions can range from several months to well over a year depending on:
- the complexity of the asset
- the need for diversion design
- service outages
- regulatory approvals
- availability of specialist resources
Utility works sometimes take many months to complete before highway construction can begin.
Additionally, due to space constraints, the construction of various civil works, resource and safety risks, all utility diversions cannot be carried out at the same time.
As a result, the development of the construction programme has considered both the utility diversion requirements, and the highway civil works sequence. This will help to ensure that activities can be delivered safely and as efficiently as possible.